The Pilbara Minerals Ltd (ASX: PLS) share price is in focus after announcing a 20-year power agreement with Fortescue Ltd (ASX: FMG) to cut operating costs and move closer to net zero emissions.

Image source: Getty Images
What did Pilbara Minerals report?
- Signed a 20-year Power Purchase Agreement (PPA) with Fortescue for a minimum of 325 GWh of electricity per year starting from 2029
- Expected unit operating costs (FOB) to decrease by approximately $15–20 per tonne compared to previous P2000 averages
- Capital investment of approximately $150 million planned, phased from FY27 to FY29, for new transmission and power infrastructure
- Power-related emissions intensity expected to drop by up to 80% (from 0.69 to 0.13 tCO₂-e/MWh) by FY30
- Transmission connection to exceed 100 MW capacity, supporting future growth and fleet electrification
What else do investors need to know?
This long-term power deal supports Pilbara Minerals' Pilgangoora Power Strategy, aiming to provide cost certainty and energy security for its core Australian lithium operation. The agreement positions the company to take advantage of increased renewables in its electricity mix and reduce reliance on diesel and gas.
Supply under the PPA will connect Pilgangoora to the Fortescue Green Grid, backed by Turner River solar power. Pilbara Minerals will fund and own a significant share of the new 25-kilometre transmission line, ensuring flexibility for further growth, including potential underground mining and electrified mining fleets.
What did Pilbara Minerals management say?
Managing Director and CEO Dale Henderson said:
We are pleased to partner with Fortescue and become their first external Green Grid customer. We commend Fortescue's leadership in bringing its vision for large-scale, lower-emissions power infrastructure across the Pilbara to life, and strongly support the opportunity for shared infrastructure to benefit industry across the region.
This agreement further strengthens our low-cost position at Pilgangoora, improving our competitiveness and resilience through lithium market cycles. Access to lower-cost, lower-emissions power will deliver further improvements to the economics of our recently approved P2000 Project expansion, beyond those announced at FID, while providing capacity to support future growth.
What's next for Pilbara Minerals?
Looking ahead, Pilbara Minerals and Fortescue will work through approvals and design to commence power supply by 2029. The improved infrastructure will future-proof Pilgangoora's expansion plans, with the aim of achieving net zero Scope 1 and 2 emissions by the 2040s.
Major capital spending will be spread over three years, with a focus on cost efficiency and enhanced sustainability. Removing a planned interim solar phase means faster emissions progress, with the company forecasting up to 80% lower power-related emissions within this decade.
PLS Group share price snapshot
Over the past 12 months, PLS Group shares have declined 6%, trailing the S&P/ASX 200 Index (ASX: XJO), which has fallen 2% over the same period.